Project Milestones - Sportsplex Renovations

  • January 31, 2023

    Facility including Squash and Racquetball Courts are fully open.
  • November 28, 2022

    Weight and stretch rooms opening!
    Squash and Racquetball courts remain closed until further notice.
  • October 31, 2022

    Sportsplex to reopen!

    Weight room and sports courts remain temporarily closed due to supply chain issues.
    October 7, 2022 News Release

  • October 24, 2022

    Certificate of Completion issued to Ketza Pacific Contracting Ltd. 

  • October 5, 2022

  • September 12, 2022 to mid-October 2022

    Due to the installation of the lighting system at Willow Point Park, the upper parking lot (off of Parkway) will be closed from September 12 until mid-October.

    Disc golf holes 17 and 18 will be closed from September 7 until mid-October. 

    Disc Golf Course Map

  • May 1, 2022

    Construction start date. The construction is expected to be complete by Fall 2022
  • March 3, 2022

    Notice to Proceed issued to Ketza Pacific Contracting Ltd.
  • February 15, 2022

    Tender 21-62 A awarded to the lowest compliant bidder, Ketza Pacific Contracting Ltd.
  • November 17, 2021

    TENDER 21-62  Sportsplex Renovations has been posted.
  • September 2021

    Design is nearing completion. We anticipate the tender for construction to be posted late fall.
  • March 23, 2020

    Please note, construction projects are on hold until further notice, in order to reduce the spread of COVID-19.
  • February 3, 2020

    Stantec Consulting Ltd. has provided City Council with three options for this work which are currently under review.
  • July 6, 2019

    Stantec Consulting Ltd. is undergoing an investigative review of the building. 
  • June 11, 2019

    RFP 19-37 Sportsplex Renovations Consulting Services - Notice of Award has been issued to Stantec Consulting Ltd.
  • May 16, 2019

    RFP 19-37 has closed and submissions are under review
  • April 23, 2019

    RFP 19-37 Sportsplex Renovations Consulting Services has been posted to the City's bid opportunities webpage 
  • March 25, 2019

    The terms of reference are currently being drafted for the RFP which is expected to be posted mid-April 2019
Featured
What's New
Jun 30, 2022 Canada Day 2022 Events
Jun 22, 2022 HOW’S THE WATER?
Jun 22, 2021 Summer Fire Safety
Feb 03, 2021 Calling young artists!
Jan 02, 2020 2019 Year-in-Review
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!
Upcoming Events