  • November 15, 2021

    Substantial Performance has been achieved on the project.
  • September 17, 2021

    Night shift work has been completed!
  • September 10, 2021

    Night work will be occurring in the downtown core from Sep. 12th to 16th to avoid disruption to businesses and traffic during the day. 
  • July 22, 2021

    All of the daytime cleaning and installation work has been completed!
  • June 1, 2021

  • February 2021

    Confirmation of the 2021 sewer rehabilitation locations is underway. We anticipate having the locations confirmed in the Spring.
  • August 9, 2020

    The contractor has reached Substantial Performance on this project.
  • July 6, 2020

    Construction has commenced.. See the steam venting during the PVC sleeve liner curing process.
  • June 19, 2020

    The 2020 Sewermain Rehabilitation project commences on June 20, 2020.
  • May 21, 2020

  • April 24, 2020

    RFP 20-18 CIPP Quality Management Specialist has been awarded to MJ Pawlowski and Associates.
  • March 23, 2020

    Please note, construction projects are on hold until further notice, in order to reduce the spread of COVID-19. For more information on the City’s response to COVID-19 please select this link.
  • February 24, 2020

    The 2020 rehabilitation program has commenced. Instuform Technologies Ltd. will be flushing, cleaning and taking video footage of the sanitary mains prior to the installation of the new sewermain liners.
  • February 21, 2020

  • January 9, 2020

    2020 Sewer rehabilitation program will be completed by Insituform Technologies. 
  • June 27, 2019

    Superior City Services Ltd. has reached Substantial Performance on this project.
  • June 3, 2019

    Pier St. evening sewermain work is resuming June 6th & 7th. See Notice of sewermain repair work
  • March 15, 2019

    Design is underway for the 2019 City Council approved locations 
  • February 19, 2019

    Work has been suspended on Pier St. as the temperature is too cold for installation of the sewer lining.   
  • February 11, 2019

    Crews are expected to be working at night in the area of St. Ann's and Island Hwy 19A (Pier St.) February 11th to 20th weather dependent. 
  • December 1, 2018

    Superior City Services night shift crew working at St. Ann’s Island Hwy intersection to Pier Street.  Crews are working evening and night shifts to avoid disruptions to businesses, parking ans traffic.
  • September 28, 2018

    Construction is scheduled to start early next week at the various locations identified on the projects overview page.
  • July 17, 2018

    Council approves award of Tender 18-25 to Superior City Services.  
  • June 21, 2018

    Tender 18-25 has closed and submissions are under review. 
  • June 19, 2018

    Tender 18-25 Addendum No. 2 has been issued
  • June 12, 2018

    Tender 18-25 Addendum No. 1 has been issued.
  • June 1, 2018

    TENDER 18-25 SEWERMAIN REHABILITATION 2018 has been posted on the city's bid opportunities page of the website.
  • April 9, 2018

    Design is underway for the 2018 rehabilitation locations.
  • September 2, 2016

    Construction is now complete on the 2016 locations.
  • August 30, 2016

    The sewermain rehabilitation cured in place pipe (CIPP) lining is underway.
  • August 15, 2016

    Video inspections of the existing sewermain are underway. 
  • July 12, 2016

    Council Approves Award of Tender 16-17 to Insituform Technologies Ltd.  
  • July 5, 2016

    Tender 16-17 has closed and the submissions are under review.
  • June 28, 2016

  • June 15, 2016

    Tender 16-17 is now posted to the city's bid opportunity page on the website.

Featured
What's New
Jun 30, 2022 Canada Day 2022 Events
Jun 22, 2022 HOW’S THE WATER?
Jun 22, 2021 Summer Fire Safety
Feb 03, 2021 Calling young artists!
Jan 02, 2020 2019 Year-in-Review
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!
Upcoming Events