Project Milestones - 6th Ave - Thulin Utility Renewal Project

  • August 29, 2023

    Utility and Paving Work Along Island Highway at 6th Avenue
    Utility and paving work will take place along the Island Highway at 6th Avenue, near the Maritime Heritage Centre, beginning Wednesday, August 30, and running until Thursday, September 14, 2023. The work is to install the last utility tie-in and complete road-surface repairs within the intersection. It will take place from 7 a.m. to 7 p.m. on weekdays; progress is weather-dependent. North and southbound traffic will be accommodated by alternating single-lane traffic flows.
  • August 23, 2023

    TEMPORARY ROAD CLOSURE ON 6th AVENUE BETWEEN ALDER STREET AND ISLAND HIGHWAY – AUGUST UPDATE

    A temporary road closure is in effect on 6th Avenue, between Alder Street and Island Highway. This work began in April and will continue until late October 2023. This closure facilitates important City infrastructure replacements to storm mains, sanitary mains, water mains, and road surfaces that will allow high quality City services to continue to be delivered into the future.

    The closure runs from 7 a.m. to 6 p.m. on weekdays. Local traffic and emergency vehicle access is available throughout. Two-way traffic has been in place for most of the work, but intermittent disruption on the Island Highway at 6th Avenue does occur, and single-lane alternating traffic is in place at times. Traffic disruption on Thulin Street between 5th and 6th Avenue may also occur. Thank you for following all traffic controls in place.

    Despite crews adapting and working longer hours when possible, the archaeological review and permitting process, supply chain issues, and contractor staffing challenges have caused delays in the project schedule. The City understands that road closures can cause disruption to daily lives, and we thank residents for their patience this summer.

    For the latest information on this project and anticipated disruptions, visit campbellriver.ca/construction, email capital.projects@campbellriver.ca or call 250-286-4033. 

  • August 17 to August 23, 2023

    Utility work along Island Highway at 6th Avenue

    Please be advised that utility work will take place along the Island Highway at 6th Avenue, near the Maritime Heritage Centre, beginning Thursday, August 17, and running until Wednesday, August 23, 2023. Work will take place from 7 a.m. to 7 p.m. daily. 

    North and southbound traffic will be accommodated at peak times, and alternating single-lane traffic flow will be in place as needed. Minor delays of between five and 10 minutes may occur. Please use alternative routes where possible, and follow the direction of the traffic control personnel and any signage in place.

    For more information, email capitalprojects@campbellriver.ca or call 250-286-5756.

  • August 10, 2023

  • August 1 to August 4

    Utility work along Island Highway at 6th Avenue

    Utility work will take place along Island Highway at 6th Avenue, near the Maritime Heritage Centre, beginning Tuesday, August 1, and running until Friday, August 4, from 7 a.m. to 7 p.m. daily.

    Please use alternate routes where possible and follow the direction of the traffic control personnel and any signage in place. Work at this intersection will be completed intermittently from now until late August 2023. Updates will continue to be provided.

    For more information, email capitalprojects@campbellriver.ca

  • April 18, 2023

    Construction begins. 
  • June 28 to June 30

    Utility work along Island Highway at 6th Avenue

    Please be advised that utility work will take place along the Island Highway at 6th Avenue, near the Maritime Heritage Centre, beginning Wednesday, June 28 and running until Friday, June 30, 2023. Work will take place from 7 a.m. to 7 p.m. daily. 

    North and southbound traffic will be accommodated at peak times and alternating single-lane traffic flow will be in place as needed. Minor delays of between five and 10 minutes may occur. Please use alternate routes where possible and follow the direction of the traffic control personnel and any signage in place. Work at this intersection will be completed intermittently from now until late August 2023. Updates will continue to be provided.

    For more information, email capitalprojects@CampbellRiver.ca or call 250-286-5756.

  • May 30 to June 3

    Utility work along Island Highway at 6th Avenue

    Please be advised that utility work will take place along the Island Highway at 6th Avenue, near the Maritime Heritage Centre, beginning Tuesday, May 30 and running until Saturday, June 3, 2023. Work will take place from 7 a.m. to 7 p.m. daily. 

    North and southbound traffic will be accommodated at peak times and alternating single-lane traffic flow will be in place as needed. Minor delays of between five and 10 minutes may occur. Please use alternate routes where possible and follow the direction of the traffic control personnel and any signage in place. Work at this intersection will be completed intermittently from now until late August 2023. Updates will continue to be provided.

    For more information, email capitalprojects@CampbellRiver.ca or call 250-286-5756.

  • March 22, 2023

  • March 28, 2023

    Notice to Proceed issued to Ecklundson Construction Ltd.
  • February 24, 2023

    Notice of Award issued to 0848631 BC Ltd. dba The Ecklundson Construction Group
  • February 8, 2023

    Tender 22-89 closed. 
  • February 3, 2023

    Addendum #4 posted to the City's Bids and Tenders website.
  • January 26, 2023

    Addendum #3 posted to the City's Bids and Tenders website
  • January 13, 2023

    Addendum #2 posted to the City's Bids and Tenders website.
  • January 6, 2023

    Addendum #1 posted on the City's Bids and Tenders website.
  • December 22, 2022

    Tender 22-89 posted on the City’s Bids and Tenders website. 
  • February 25, 2022

    Geotechnical investigations are complete.

  • January 10, 2022

    Project Design process is underway.

Featured
What's New
Jun 30, 2022 Canada Day 2022 Events
Jun 22, 2022 HOW’S THE WATER?
Jun 22, 2021 Summer Fire Safety
Feb 03, 2021 Calling young artists!
Jan 02, 2020 2019 Year-in-Review
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!
Upcoming Events