WM LogoSlantedPostProject Progress Diary

Keep up-to-date on progress, events and milestones related to the Watermain Replacement Projects.

 

 

Please contact the project team at capitalprojects@campbellriver.ca if you have any questions or concerns.

Project Milestones - Watermain Replacement

  • January 24, 2017

    This project is currently on hold due to other strategic priorities.
  • January 17, 2017

    Design is nearing completion for the Garfield, Painter and Pengelly Road area.
  • July 19, 2016

    Design continues on the remaining watermain replacement locations for construction in 2017.
  • July 6, 2016

    The new watermain is installed and paving is complete on Cedar Street!
  • June 16, 2016

    Locating underground utilities with a vacuum truck.
  • June 14, 2016

    The new watermain has been delivered and is now being installed.  
  • June 13, 2016

    The contractor is now on site and construction has begun on Cedar Street!
  • June 7, 2016

  • May 24, 2016

    Council Approves Award of Tender 16-34 to JR Edgett Excavating Ltd. 
  • April 26, 2016

    Tender 16-34 for construction of the Cedar Street watermain replacement is now posted to the City's bid opportunities page on the website 
What's New
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!
Upcoming Events