SewerPROJECT PROGRESS DIARY

Keep up-to-date on progress, events and milestones related to the Waterfront Sewer Forcemain Upgrade Project.

Email us at: capitalprojects@campbellriver.ca

 

Project Milestones - Waterfront Sewer Forcemain

  • October 2019

    Construction work in the corridor wraps for the year.

  • September 12, 2019

    A midden is found during excavation work near Rotary Beach Park. Reporting is completed and permitting process begins.
  • August 2019

    Crews officially transition over from the Highway Upgrades underground work, to the installation of waterfront sewer pipe.

  • August 21, 2019

    An Open House and online survey is held regarding shared road use between 5th and 6th avenues. Feedback to be collated and provided to staff/council for consideration in future decisions.

  • April 24, 2019

    Tender 19-07 has been approved by City Council and awarded to Wacor Holdings Ltd.
  • April 12, 2019

    Tender 19-07 Waterfront Sewer Upgrades Phase II has closed and submissions are under review.
  • April 11, 2019

    Tender 19-07 Waterfront Sewer Upgrades Phase II Addendum No.4  
  • April 4, 2019

    Tender 19-07 Waterfront Sewer Upgrades Phase II Addendum No. 3
  • March 28, 2019

     Tender 19-07 Waterfront Sewer Upgrades Phase II Addendum No. 2
  • March 21, 2019

     Tender 19-07 Waterfront Sewer Upgrades Phase II Addendum No.1
  • March 20, 2019

    TENDER 19-07 Waterfront Sewer Upgrades Phase II has been posted on the city's bid opportunity webpage
  • October 24, 2018

  • September 11, 2018

    Pipe installation reaches mid-point of the route (4th Ave)
  • July 9, 2018

    Construction starts near the entrance to Maritime Heritage Centre
  • June 12, 2018

    City Council approves award of Tender 18-13 to J. Cote & Son Excavating Ltd.
  • May 28, 2018

    Tender 18-13 closed and is under review. 
  • May 24, 2018

    Tender 18-13 Addendum No. 5  has been issued.
  • May 22, 2018

    Tender 18-13 Addendum No. 4  has been issued. Tender close date has been extended to May 28, 2018.
  • May 18, 2018

    Tender 18-13 Addendum No.3 has been issued.
  • May 17, 2018

    Tender 18-13 Addendum No. 2  has been issued.
  • May 1, 2018

    Tender 18-13 Addendum No. 1  has been issued. Tender close date has been extended to May 24, 2018. 
  • April 27, 2018

    TENDER 18-13 for Phase 1 construction has now been posted on the city's bid opportunities webpage!
  • January 9, 2018

    City Council approves award of RFP 17-68 to Zinc Communications Strategies
  • December 8, 2017

    RFP 17-68 closed and is under review
  • November 30, 2017

    RFP 17-68 Communications Consultant Addendum No.1 has been issued
  • November 9, 2017

    RFP 17-68 For a Communications Consultant has been posted to the City's bid opportunities webpage!
  • September 20, 2017

    Design is currently underway by Stantec Consulting Ltd.
  • July 10, 2017

    City Council approves award of RFP 17-30 to Stantec Consulting Ltd.
  • May 17, 2017

    RFP 17-30 Closed and under review. 
  • April 19, 2017

    RFP 17-30 For design is posted to the City's bid opportunities website page!
What's New
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!