Project Progress Diary

Keep up-to-date on progress, events and milestones related to the NWEC Biosolid Site Management Project.

Please contact the project team at capitalprojects@campbellriver.ca if you have any questions or concerns.

Project Milestones - NWEC Biosolid Site Management

  • January 16, 2019

    Design is underway for field II.  
  • July 8, 2019

    Wacor Holdings Ltd.has achieved Substantial Performance on this project
  • June 25, 2019

    The pivoting biosolid spreader on the freshly stripped field. 
  • May 14, 2019

    Tender 19-15 Biosolid Site Management Phase 1 has been awarded to Wacor Holdings Ltd.
  • May 2, 2019

    Tender 19-15 has closed and submissions are under review 
  • April 17, 2019

    Tender 19-15 NWEC Biosolids Site Management Phase 1 has been posted to the City's Bid Opportunities web-page.
  • March 15, 2019

    RFP 19-20 Timber Stand Assessment & Removal awarded to Integrated Operations Group Inc,
What's New
Jan 02, 2020 2019 Year-in-Review
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!